Oracle proposes 35% emissions reduction at New Mexico data center

Published

 

on

Oracle's office in Silicon Valley.

Oracle proposes a 35% emissions cut

Oracle and Yucca Growth Infrastructure proposed changes to Project Jupiter’s power system on October 15, 2026. The revisions would reduce modeled emissions by approximately 35%, subject to regulatory review.

The announced reduction concerns a proposed fuel cell microgrid, not pollution measured at an operating facility. Final emissions limits would depend on the state’s approval of revised operating conditions.

Data center under construction.

A large data center takes shape

Project Jupiter is a data center campus under construction near Santa Teresa, New Mexico. STACK Infrastructure is developing the computing buildings being leased to Oracle for OpenAI workloads.

BorderPlex Digital Assets participated in earlier development plans, but Oracle reportedly removed it as a project partner. The proposed microgrid occupies an adjacent site and requires separate permits.

A view of a natural gas power plant.

Developers changed the power design

Oracle’s earlier power proposal relied on natural gas turbines and backup generators. In April 2026, developers switched to Bloom Energy fuel cells for the planned large computing campus.

The New Mexico Environment Department issued its application-completeness letter on May 27, 2026, and public review opened in June. Completeness did not mean that the requested permit was approved.

Construction of a new oil pipeline.

Fuel cells depend on a proposed pipeline

Bloom Energy’s fuel cells would convert natural gas into electricity through an electrochemical process rather than conventional combustion. Developers plan an on-site microgrid intended to power Project Jupiter.

The system would require a proposed natural gas pipeline that had not been constructed when the application was reviewed. That infrastructure involves separate approvals beyond the microgrid permit.

Inside view of a bitcoin data center.

An operating cap drives the change

The latest revisions propose a limit on the fuel cells’ electrical output, measured in megawatts. Developers expect that operating restriction to reduce modeled emissions from the power facility.

Oracle maintains that the operating cap would preserve the campus’s planned computing capacity. The company says its revisions introduce no new pollutants or types of equipment to the design.

Fun fact: Without water-saving measures, data centers could use 644 billion liters of water globally each year by 2030.

Smoking chimneys of a chemical plant emitting large amounts of greenhouse gases, symbolizing air pollution.

Greenhouse gas estimates fall sharply

Under the revised proposal, projected annual greenhouse gas emissions would decrease from about 8.8 million tons to 5.7 million tons. Both amounts describe modeled pollution, not actual measurements.

The difference exceeds 3 million tons per year under the developers’ assumptions. State regulators must evaluate the revised calculations before deciding whether the proposed facility meets applicable requirements.

Little-known fact: A medium-sized data center can use up to 300,000 gallons of water daily for cooling, about 1,000 households’ use.

A woman checking the outdoor air quality index using an app on her smartphone. Selective focus.

Proposed reductions cover other pollutants

The developer also forecasts reductions in nitrogen oxides, carbon monoxide, and volatile organic compounds. These pollutants are included in the New Mexico Environment Department’s ongoing air quality review.

The revised proposal also estimates lower particulate matter and hazardous air pollutants. Even with those changes, regulators must examine each category against the applicable state and federal permit requirements.

Government officials in a meeting.

State reviewers questioned the application

The New Mexico Environment Department’s Air Quality Bureau raised technical questions during its review of the application. Public comments also identified issues requiring further examination by state regulators.

Yucca Growth Infrastructure submitted additional materials to supplement its pending air permit application. Regulators must assess the updated documents and resolve outstanding questions before issuing a final decision.

Officials at a meeting.

New modeling raised additional concerns

Updated modeling in the administrative record predicted higher concentrations of certain air pollutants than earlier estimates. Agency correspondence questioned previous assumptions supporting the initial assessment of possible impacts.

In correspondence dated October 2, a state attorney identified approximately 2% higher modeled emissions but roughly doubled predicted pollutant concentrations. Those figures assess different aspects of the analysis.

Government officials at a meeting.

An advocacy group seeks dismissal

On October 14, New Energy Economy requested dismissal of the pending air permit application. The Santa Fe organization disputed whether the technical record was adequate for a decision.

Attorney Mariel Nanasi challenged the reliability of revised pollution modeling and earlier assumptions. Her filing represented an argument in the permitting dispute, not a final ruling by regulators.

Judge holding lawsuit documents near advocate and prosecutor.

A hearing remains on the calendar

Retired federal Judge James O. Browning replaced Max Shepherd as hearing officer following Shepherd’s recusal. Deputy Cabinet Secretary John Rhoderick retains final decision-making authority over the pending microgrid permit.

On October 16, Browning scheduled the main air permit hearing for December 7 in Sunland Park. He also scheduled an October 26 hearing to consider pending dismissal motions.

Oracle logo on a building.

Oracle outlines future climate goals

Oracle committed to 100% carbon-free energy matching for Project Jupiter by 2031. This planned matching arrangement would not automatically eliminate direct emissions from natural gas used at the site.

Oracle also pledged to align Project Jupiter with New Mexico’s Energy Transition Act goals before 2045. Those statutory electricity standards apply to regulated utilities, making the company’s commitment voluntary.

Want to read more about the latest developments? Check out how Trump’s new solar import rules could raise project costs and affect what Americans pay for solar next year.

People at a round table session.

Future monitoring remains a commitment

Oracle plans a public dashboard displaying air quality, noise, heat, lighting, and water data once Project Jupiter operates. The company promises the reporting system will receive independent verification.

Public reporting would provide operational evidence distinct from the forecasts reviewed during permitting. Until the facility operates and actual measurements become publicly available, those monitoring commitments remain prospective.

Want to stay ahead of the news? Check out how it could take a first-time NYC homebuyer more than 65 years to save enough.

What stands out more, Oracle’s proposed 35% emissions reduction or the continued reliance on natural gas at its New Mexico data center? Share your thoughts in the comments below!