North Dakota data center plan near Fargo raises power questions as demand could reach 540 megawatts

Published

 

on

An aerial view of a data center.

Harmony Energy Park enters review

Geronimo Power proposed Harmony Energy Park, a data center in Harmony Township near Mapleton. The project is expected to receive up to 540 megawatts of initial electrical service.

The company filed for a conditional use permit, placing the proposal under local review. The site is near the Bison Substation and existing 345-kilovolt transmission infrastructure in Cass County.

Overhead power lines.

Harmony lists 540 megawatts of service

Geronimo Power compares Harmony with Applied Digital’s Polaris Forge 2 project near Harwood. Applied Digital uses separate measures for contracted load, construction capacity, and broader campus development.

Applied Digital describes Polaris Forge 2 using metrics that differ from Harmony’s electrical service figure, so a direct like-for-like capacity comparison between the two projects would be misleading.

A view of empty land.

Site plan covers about 640 acres

The proposed site covers about 640 acres and would include two main data center buildings with supporting infrastructure. Final component locations may change after additional engineering and design work.

Geronimo Power expects construction to take about two to four years. Work must begin within 48 months after permit approval unless Harmony Township grants an extension for development.

Water based cooling system on a data center's roof.

Daily water demand could reach 20,000 gallons

Geronimo Power estimates employee water use at about 15,000 gallons daily. Peak demand could approach 20,000 gallons under the proposed facility design during periods of higher use.

Cooling would use a closed-loop system that recirculates fluid instead of continuously consuming water. Geronimo Power plans to obtain the initial fill from a qualified off-site supplier before operations.

A view of battery storage units.

New power resources are expected

Geronimo Power expects new power resources to serve the proposed data center. Potential resources include renewable electricity, battery storage, and natural gas, each subject to separate regulatory approvals.

The company expects added generation to support the large electrical load. Any associated generation facilities would need their own permitting and regulatory review before they could be developed.

Officials at a meeting reviewing documents.

Otter Tail tariff remains pending

Otter Tail Power Company proposed a large-load tariff for qualifying data centers. The filing would assign service costs linked to those facilities directly to qualifying data center customers.

The North Dakota Public Service Commission is reviewing the proposal. Final tariff terms remain pending until regulators complete the formal process and issue an order in the case.

Fun fact: Data centers can consume 10 to 50 times more energy per square foot than a typical office building.

Engineer working at a solar farm.

Harmony Solar is under construction

Harmony Solar, a 200-megawatt project beside the Bison Substation, is under construction. Geronimo Power is building the facility near the proposed Harmony data center area north of Mapleton.

The solar project received state siting approval years before Harmony Energy Park emerged. Its location places generation development beside the proposed data center site near Mapleton in Cass County.

Little-known fact: Modern data centers trace their roots to the 1940s, when ENIAC required dedicated space and controlled conditions.

A row of battery storage units.

Harmony Storage awaits state review

Geronimo Power also proposes Harmony Storage, a 200-megawatt battery system in the township. The facility would store nearby solar electricity for up to four hours during normal operation.

The North Dakota Public Service Commission scheduled an October 23 hearing in Casselton on the application. The battery project needs separate state approval before construction can begin there.

Transmission towers and lines.

Regional infrastructure remains proposed

The proposed Big Stone South to Hankinson to Bison transmission line would connect with the Bison Substation near Mapleton, adding another planned regional electricity project to the area.

WBI Energy is advancing the proposed Bakken East Pipeline from western North Dakota to a compressor station near Mapleton. The project remains in the federal pre-filing review process.

Person pointing with a pen at a map.

Township revisits zoning changes

Earlier local zoning changes involved data center noise rules and setback requirements. Those revisions also changed how some nonresidential buildings near the proposed site were treated within setback areas.

Township officials are seeking legal guidance on whether those zoning revisions could be affected by questions about the ordinance process and prior ordinance votes in Harmony Township.

Officials at a board meeting.

Roden agreement remains part of review

Questions also involve former township supervisor Tom Roden’s land agreement and his participation in ordinance votes connected with the proposed site. The matter has not reached a final township determination.

The pending permit remains separate from any final legal determination on earlier zoning actions. Harmony Township still must decide how to proceed with the proposed site.

A meeting of government officials

October township meeting remains scheduled

The Harmony Township Board of Supervisors is scheduled to meet October 20. The agenda leaves open whether the data center proposal will appear before officials at that meeting.

The meeting remains separate from state utility and siting proceedings. Any zoning or permitting action would depend on matters formally placed before Harmony Township officials for formal consideration.

Want to read more about the latest news? Check out how the Northeast cap-and-trade debate turned toward wind setbacks and transmission limits.

People at a meeting.

Community outreach continues

Geronimo Power scheduled Casselton office hours for October 6 and October 7, giving residents additional opportunities to ask questions while the proposed data center moves through local review.

Additional outreach is planned for October 8. Geronimo Power has invited residents to discuss the proposal as the company continues public engagement during the ongoing local permit process.

Want to stay ahead of the news? Find out what changed after a Massachusetts city backed a $4B data center and then approved a unanimous moratorium.

Do you think Harmony Energy Park will advance North Dakota’s infrastructure planning, or raise new questions about 540 megawatts of demand, local permits, and power costs? Share your thoughts.

This slideshow was made with AI assistance and human editing.

Read More From This Brand:

Trending Posts