North Dakota pipeline ruling could affect future power-line disputes

Published

 

on

Judge hears attorneys during courtroom proceeding.

Local zoning gets new weight

A North Dakota judge ruled on October 9, 2026, that state pipeline siting authority does not automatically override county zoning ordinances governing proposed carbon dioxide pipeline routes within affected counties.

Landowners, Emmons County, and Burleigh County brought the lawsuit against the North Dakota Public Service Commission and Summit Carbon Solutions over a pipeline route permit issued in November 2024.

A meeting of government officials.

County setbacks remain central

Bismarck attorney Derrick Braaten represented Emmons County in the lawsuit. He described the ruling as support for local government authority to establish pipeline setbacks near occupied residential buildings.

Setbacks determine the minimum distance between a proposed route and homes or other structures. The legal dispute examined whether state approval could supersede these existing county zoning restrictions.

A binder labelled as consisting of permits.

Permit remains in place

South Central Judicial District Judge Jackson Lofgren left Summit’s November 2024 route permit in place while directing state regulators to revisit several findings challenged in the original lawsuit.

The order required additional findings on public welfare, an alternate route through Burleigh County, access to Summit’s plume model, and the reasonableness of specific setbacks in two counties.

Government officials in a meeting.

Public welfare needs fuller review

The North Dakota Public Service Commission must better explain why the approved pipeline route would not impair public welfare, including evidence tied to possible safety concerns during siting review.

During a July 2026 hearing, an agency attorney argued that federal regulators enforce pipeline safety standards. The ruling requires a fuller explanation of public welfare considerations during route decisions.

Engineers installing heavy pipeline.

Alternate route needs review

Judge Lofgren found that regulators had not adequately explained why they considered an alternate pipeline route through southern Burleigh County sufficiently examined before granting Summit its original permit.

This unresolved question concerns the commission’s assessment of another possible path, rather than an order requiring Summit to adopt that alignment or abandon its previously permitted pipeline corridor.

Officials at a meeting reviewing documents.

Plume model faces disclosure

Summit developed a plume dispersion model estimating how carbon dioxide could spread after a rupture in its proposed high-pressure pipeline. Regulators initially kept the detailed document confidential during proceedings.

The judge required either a redacted public version or a stronger explanation for withholding it, considering evidence that Summit had shared access with some members of the public.

Fun fact: The United States currently has about 5,000 miles of pipelines carrying carbon dioxide across the country.

A gavel on a desk with a judge reading documents in the background.

County ordinances require findings

The court instructed the Public Service Commission to determine whether setback ordinances adopted by Emmons and Burleigh counties are unreasonably restrictive under North Dakota’s pipeline siting statutory framework.

State siting standards may supersede county requirements if regulators find local limits unreasonably restrictive. The commission must make that specific determination during further regulatory review of this case.

Little-known fact: In the U.S., transmission projects that require entirely new lines often take 10 years or more to complete.

Transmission towers and lines.

Power line rules raise questions

North Dakota lawmakers amended state siting law in 2025 to apply similar local zoning and preemption standards to electric transmission facilities reviewed by the Public Service Commission for approval.

Under that framework, an approved transmission permit may supersede county requirements when regulators determine those local rules are unreasonably restrictive or directly conflict with state or federal law.

A view of transmission towers and lines.

JETx provides a related example

Local zoning preemption became an issue during hearings for JETx, the Jamestown to Ellendale transmission project. North Dakota regulators granted its corridor and route permits on June 24, 2026.

The approved 345-kilovolt transmission route covers approximately 92 miles between substations near Jamestown and Ellendale. Its planned corridor crosses Stutsman, LaMoure, and Dickey counties in southeastern North Dakota.

Professionals in a meeting.

Issues return to commission

At the time of the October 9 order, the Public Service Commission’s legal team was reviewing the court’s findings and weighing the agency’s next steps after the remand.

Because the November 2024 permit remains effective, the remand concerns unresolved agency explanations and determinations. Further action depends on how regulators address the court’s specified deficiencies on remand.

Overhead power lines.

South Dakota setback reshaped route

Summit’s earlier plan depended on a South Dakota crossing to reach North Dakota storage. In May 2026, the company instead prioritized a westward route through Nebraska to Wyoming.

South Dakota regulators rejected Summit’s application in April 2025, and state law now bars eminent domain for carbon dioxide pipelines. Summit says South Dakota remains possible for future phases.

Judge holding a wooden gavel in court.

Storage appeal narrows options

In March 2026, Judge Lofgren ruled that portions of North Dakota’s carbon dioxide storage law were unconstitutional and set aside permits covering three separate proposed underground storage areas.

The North Dakota Industrial Commission approved cancellation of two storage permits, while Summit’s appeal concerning the third remains pending before the North Dakota Supreme Court in related litigation.

Want to read more about the latest developments? Check out how the South Dakota data center law put local water and power authority in debate.

A meeting of government officials.

Summit announces Wyoming storage route

Summit announced in May 2026 that its streamlined project would travel west through Nebraska toward dedicated carbon dioxide storage in Wyoming, placing the state at the system’s core.

North Dakota, South Dakota, and Minnesota remain possible future phases, according to Summit. For now, the company’s stated priority is the Nebraska-Wyoming route rather than its original system.

Want to stay ahead of the news? Check out how Pennsylvania bills target data center costs and utility profit rules.

As North Dakota regulators revisit local zoning and state siting authority, should counties have greater control over pipeline and power-line routes? Share your thoughts in the comments below!