Virginia transmission line dispute reaches new stage over school and neighborhood routes

Published

 

on

Overhead power lines.

New routes enter the dispute

U.S. Representative Suhas Subramanyam asked Virginia regulators on October 9 to examine three new paths for Dominion Energy’s Golden to Mars transmission project in Loudoun County.

The alternatives seek to move the high-voltage corridor away from residential yards and school property. The State Corporation Commission has not replaced its approved Route 3A.

Transmission towers and lines.

Project completes reliability loop

Golden to Mars would connect the Golden and Mars substations with new 500- and 230-kilovolt transmission infrastructure across eastern Loudoun County near Ashburn and Dulles International Airport.

Dominion Energy describes the project as the final segment of its Loudoun Reliability Loop, a three-project network intended to strengthen electric service as regional demand grows.

Government officials at a meeting.

Route 4 came first

The State Corporation Commission authorized the project on April 9 and identified Route 4 as the option that best served the total public interest among routes reviewed.

Route 4 depended on permission from the Loudoun County School Board because the alignment required school property. Regulators identified Route 3A as the fallback without that consent.

Government officials in a meeting.

Regulators selected Route 3A

The commission issued its final order on June 29 after the School Board had not approved Route 4. Regulators then selected Route 3A for construction in Loudoun County.

Commissioners said further delay would unreasonably jeopardize reliable electric service in Virginia. The final order kept Route 3A in place while opponents pursued separate legal challenges.

People at a round table session.

School Board rejected voluntary use

The Loudoun County School Board met on July 13 and adopted a policy against voluntarily allowing electric transmission or power-line facilities on property owned by the school division.

Board members also authorized legal action over the Route 3A decision. That step followed months of concern about routes near Rock Ridge High School and Rosa Lee Carter Elementary.

Power lines rise behind suburban homes beneath a blue sky.

Neighborhood effects drive opposition

Route 3A runs between Rock Ridge High School and the Loudoun Valley Estates residential community and affects private property and nearby open space. Residents have argued that the alignment places large transmission structures too close to homes and community facilities.

Their opposition has continued through regulatory filings and appeals challenging the selected route. Some property owners face substantial changes to their yards and surrounding vegetation if the approved alignment is constructed.

Fun fact: The United States has approximately 2.7 million transmission towers, alongside 180 million utility poles and 450,000 miles of power lines.

Transmission tower silhouetted against an intense orange sunset during extreme heat.

Alternatives shift toward Dulles

Subramanyam’s October proposal includes paths following Old Ox Road, also known as Route 606, and routes west of Dulles International Airport that would cross federal property.

The three alternatives were presented as ways to reduce effects on homes and schools. The State Corporation Commission has not approved them, and Dominion has not adopted them as project routes.

Little-known fact: Transmission towers use porcelain or glass insulators to support high-voltage cables and keep steel structures electrically isolated.

National Oceanic and Atmospheric Administration's logo on a phone screen.

NOAA property enters discussion

One proposed path would cross National Oceanic and Atmospheric Administration property west of Dulles runways and near the agency’s WSR-88D Doppler radar installation in Sterling, Virginia.

Subramanyam said NOAA Administrator Neil Jacobs told him during a July 20 meeting that the agency had no technical objection to a route near the radar.

Federal Aviation Administration website displayed on a computer screen.

FAA review adds another factor

Subramanyam also said the Federal Aviation Administration was conducting an obstruction evaluation involving a Dominion route near Dulles. Such reviews examine potential effects on navigable airspace.

Subramanyam asked state commissioners to consult federal agencies directly about feasibility. Any federal review would inform route considerations but would not itself change the approved transmission alignment.

Officials at a meeting reviewing documents.

Appeals challenge final order

The Route 3A order has faced appeals from local parties, including Loudoun County, the School Board, and neighborhood groups. The final order remained on appeal in October.

The appeals challenge the commission’s final order, while Subramanyam’s request asks regulators to revisit route choices with federal agencies. The two tracks remain separate parts of the dispute.

Red utility conduits lie in trenches during underground cable installation.

Underground option remains disputed

Residents and local officials previously pressed for underground construction. The commission rejected an underground Golden to Mars route after reviewing cost, engineering, space, and transition-site requirements.

Virginia legislation effective July 1 expanded a pilot program for underground 500-kilovolt lines. A participating locality generally must cover at least 50% of marginal costs within its boundaries.

Stacks of dollar bills.

Cost and schedule shape pressure

The Golden to Mars project is estimated to cost more than $500 million. Dominion’s desired in-service target is June 2028, subject to permitting and scheduling changes.

The commission has treated the project as an urgent reliability need. Dominion says the broader loop is designed to strengthen service as electricity demand rises across Northern Virginia.

Want to stay ahead of the news? Check out how Connecticut’s power prices fall while data center demand lifts costs elsewhere.

Transmission towers rise behind suburban homes beneath clear blue skies.

Route 3A remains approved

Route 3A remains the commission-approved path unless legal or regulatory action changes it. Subramanyam’s three alternatives are requests for additional review rather than authorized construction routes.

Further decisions may depend on state regulators, pending appeals, federal property questions, and aviation review. Until those processes change the record, Dominion’s approved route remains Route 3A.

Want to read more about the latest developments? Check out how the Indiana Duke Energy case could affect solar groups and utility lawsuits.

Do you think Virginia should reconsider Route 3A to reduce impacts on schools and neighborhoods, or should the approved transmission route remain in place? Share your thoughts in the comments below!

This slideshow was made with AI assistance and human editing.